Case studies / A thermal power plant
POWER AND UTILITIES
A thermal power plant
Office IT and the plant's DCS and SCADA estate inventoried together and scoped for gap analysis, threat assessment and testing.
- SECTOR
- Thermal power generation, Vidarbha
- ENGAGEMENT
- IT and OT vulnerability assessment, 2022
- NILWIRE'S ROLE
- Consulting, with a CERT-In empanelled auditor carrying out the testing
THE SITUATION
Two worlds on one site.
The plant combines an office IT network with operational technology: a distributed control system for each unit, a SCADA system, and remote units that report over IEC 60870-5-101 and 104.
What we did
One picture of IT and OT.
NilWire collected the estate in two inventory sheets, one for IT and one for OT across the main plant and the switchyard, and gathered the drawings that show how IT, DCS and SCADA connect. The OT scope covers eleven subsystems, from ash and coal handling to water treatment and hydrogen generation.
Phase 1
A study of the as-is environment through documents, discussions with key personnel and a view of the systems in operation.
Phase 2
Gap analysis, threat assessment, and vulnerability assessment and penetration testing of IT and OT network devices.
WHAT THE PLANT RECEIVES
An executive summary and a technical record.
An executive summary of critical vulnerabilities, remediation and the positive security aspects found, and a detailed technical section covering every weakness with its remediation.
THE STACKS INVOLVED
Where this work sits in the chain.
RELATED
Continue reading.
Vertical
MSM manufacturing
Machines connected as they stand, through one controlled path into IT.
Vertical
MSM manufacturing →Case studies
All case studies
Two named flagships and more engagements described by sector, region and scale.
Library
All case studies →Consulting · first engagements
See how a first engagement works.
Start small, prove it, then scale. Six small engagements, each with a plain question and a written plan.